Task Master Task Assignments

Task Master Task Assignments

Return to Configuration Overview

You can calculate task assignments based on three options:

hw45-2010-timeline1.jpg

These options give you more flexibility when assigning tasks and building schedules. They are located in the tool pane under Dependency Settings.

Use the following table to decide which option to choose.

Task Type If Duration is modified If Work is modified If Assignment Units is modified
Fixed Work Task Assignment Units is recalculated Duration is recalculated Duration is recalculated
Fixed Duration Task Work is recalculated Assignment Units is recalculated Work is recalculated

Calculate resources method: In Task Master (Release 3.5 and above), you can choose how task resources are calculated when resources are added or removed from an existing task. These options give you more flexibility when assigning tasks and building schedules. They are located in the tool pane under Dependency Settings.