Overview of Project PMC Control Panel

Resource Center links in the Control Panel
From the PM Central Control Panel, you can access the Resource Center, with direct links to three of the five available subsections.

NOTE: The Resource Center will not be available under PM Central General Settings if the project site was created using a Lite or Stand-alone template.

The Resource Center in PMC

Function
1.

The Project Team Info tab displays a view of the sites Contacts list that stores user information for the resources associated with the project.

Project Managers can:

2.

Under the Resource Assignments tab you will find a Gantt display of all tasks for all projects sorted by resource.

  • For information on using the web part click here.

  • For information on changing the number of items per page, click here.

3. The Resource Allocation and Capacity Planning tab provides access to a number of reports detailing resource capacity, allocation by resource, project, resource availability and others.
4.

Users who are not part of the portfolio’s Enterprise Resource Pool, can be added in bulk to the Project Resource pool using the User Profile Import utility.

NOTE: Use of this tool requires a modification to the default behavior of the Bamboo Role column. Click here for more information.

4. Copy Resources provides a tool to import multiple resources simultaneously from the Enterprise Resource Pool